top of page

Locations: Parsippany, NJ; Cumberland, RI; Whippany, NJ

​

Size: A New 300,000-sf Customer Fulfillment Center

​

Project Type: Supply Chain

​

Website: https://www.tiffany.com/

​

Accomplishments:

  • Managed the specification, procurement and installation of over $37M equipment purchased.

  • DC reduced order turn time from 4 days to 3 hours.

  • Reduced average cost / unit for processing by over 50%.

  • Hands-off print and apply outbound labeling increased throughput and reduced labor.

  • Labor savings in excess of 38%.

  • Created ergonomic workstations with new patented roll-feed technology.

suburu, bic inc, industrial consulting, danvers massachusetts, boston industrial consulting, supply chain, facility transition, tiffany

Related Case Studies

Screen Shot 2024-04-12 at 7.48.10 PM.png
Copy of home build construction logo.png

The Boston Industrial-Philips relationship began in 1996 when BI assisted Philips (formerly Hewlett Packard) with supply chain and manufacturing projects for its Healthcare Systems Group located on the Andover, MA campus.  The relationship extends over 17 years and 22 projects.

Screen Shot 2024-04-12 at 9.22.12 PM.png
2.png

Design and implement AMR robots to automate material handling in the Indianapolis facility. Also, assisted Spartanburg with conversion of batch picking to a continuous wave pick operation.

Screen Shot 2024-04-12 at 9.10.28 PM.png

​

3.png

Implemented a new racking, material handling, process design and Warehouse Control system, including voice picking and conveyor automation. Managed the implementation of Build-to-Suit control software and new Pick/Pack system.